Description: This project was completed in April 2006. The project consisted of the complete plumbing and HVAC construction of a 100,000 square foot chilled warehouse for Minute Maid products, including a 3,000 square foot office area.
Highlights:
- The project was completed on a design / build basis using a team approach between the engineer, Alberici Constructors and Group 92.
- The project was under budget and completed on time.
- Specific attention to scheduling was required due to ongoing plant operations and the transfer of production.
Engineer: Vanderwesten, Rutherford, Mantecon Engineering